SALES & CONSTRUCTION UPDATE
It’s been another productive month on site for the Haymont team, with Stages 1 and 2 achieving practical completion and works progressing smoothly in Stage 3!
In Stages 1 and 2, asphalting works are complete and Practical Completion has been achieved. The team is currently closing out final Authority approvals ahead of Statement of Compliance and Title Registration.
In Stage 3, external water installation works are now complete, with sewer installation works ongoing. Drainage works are set to commence in the coming weeks.
We are currently selling through the final remaining lots in Stage 3, with Release 5A lots also now available! So, if you’re interested in joining the growing Haymont community, contact our friendly team today on 03 9684 8190 or email [email protected].